The original cost to build City Hall was approximately
$17 million.
This page includes current information about the City Hall reclad project timeline. Placing your mouse over a project phase in the graphic below will highlight the section of the building that will be affected during that phase. Clicking on a project phase below will take you to that phase in the timeline where you can find related dates and activities.
PhaseI
Erect scaffolding at southwest corner of tower
June 2003
July 2003
- Erect scaffolding at
southeast corner of tower
- Start mechanical work
Startwork on western half of tower at Broad Street
September 2003
October 2003
- Start work on southern half of 9th Street side
- Erect scaffolding at northwest corner of tower
Phase II
- Start work on eastern half of tower at Broad Street
- Work on tower at southwest corner completed
- Start work on southeast quadrant
December 2003
January 2004
- Start work on southern half of tower at 10th Street
- Erect scaffolding at northeast corner of tower
Phase III
- Start work on northern half of tower at 9th Street
- Start work on northeast quadrant and Council chambers
February 2004
March 2004
-Work on southeast quadrant completed
- Work on eastern half of tower at Broad Street completed
- Start work on northwest quadrant
- Start work on Broad Street entrance canopy
April 2004
May 2004
-Start work on northern half of tower at 10th Street
- Work on southwest quadrant completed
Phase IV
- Work on southern half of tower at 10th Street completed
June 2004
July 2004
- Start work on tower at Marshall Street
- Work on northern half of tower at 9th Street, north-east quadrant and Council Chambers completed.
August 2004
November 2004
Phase V
- Start work on 10th Street entrance canopy
- Work on northwest quadrant/Council chambers completed
December 2004
January 2005
- Start work on 9th Street entrance canopy
- Work on Marshall Street completed
- Work on 10th Street entrance canopy completed
February 2005
April 2005
- Work on 9th Street Entrance canopy completed
PROJECT COMPLETION
June 2005